What Should You Buy Out First On A Job?

Windows, doors, HVAC units, switchgear, steel and engineered lumber get bought out first. Then level the rest against your estimate and sign every sub.

3 min read

Buy out the long lead scopes first. That means windows, doors, HVAC units, electrical switchgear, structural steel and engineered lumber. Get those ordered right away, then level and award the rest of the trades against your estimate. Every sub gets a signed subcontract before he starts work.

Most contractors buy out trades randomly. They find the scope gaps after the sub has started. By then it's too late to negotiate, and they eat the cost.

Why do long lead items go first?

Because if you wait until you need a window package or an HVAC unit, your crew ends up waiting on it.

One of the contractors in our mastermind saw this on his own jobs. His team used to order materials when they needed them. Things got forgotten, and an item would be four weeks out when they were ready for it in a week.

Now he holds a preconstruction meeting every Friday for each newly deposited job, and his office manager orders everything right then. He told us the only downside is that things show up before they need them.

Long lead items are where that wait hurts the most. So tell your PM to buy those out first, on every job.

What happens during buyout?

Buyout is where the project manager takes the job from estimating and locks in every trade. He reviews the handoff documents from estimating and puts the long lead items at the top. Then he levels and negotiates the proposals against the estimated amounts, and documents every award decision.

Bid packages in Structur go out to vendors you filter by trade. The scope and drawings get uploaded once for all of them. Each vendor submits pricing through a link, with no account needed. The leveling tab puts every bid side by side by cost code, so you're comparing the same scope.

How does the PM know what's left in the budget?

The project manager should always know the available budget in each cost code while he's buying out the job. Structur's budget shows the available budget for every cost code, with the project total at the bottom. Each subcontract line shows its cost code's available budget too.

That budget is raw cost, with your overhead, internal markup and profit left out. So give your PM that base number. If he buys a scope out under it, the difference is profit the job keeps.

When does a sub get his subcontract?

Before he sets foot on your job site. The subcontract references the specific scope, drawings and specifications for that trade. It also spells out payment terms, insurance requirements, schedule obligations, change order procedures and cleanup standards.

Most contractors let subs start work on a handshake, and then disputes happen. When there's a forty thousand dollar disagreement, the contractor without a signed subcontract loses every time.

An awarded bid converts to a subcontract in Structur in two clicks. Your default terms and conditions apply to every new one. The vendor gets an email, opens the subcontract and approves it by signing.

On the next job you sign, sit down with your PM before the first bid package goes out. Write the long lead list together and get those orders placed that week.