How To Price Your Superintendent And PM Into A Bid
Your superintendent and PM are a cost of the job. Price them by the week in general conditions, on their own lines, and the client pays for them.
Your superintendent and your project manager go in general conditions on every bid, priced by the week. They're a cost of the project, so the client pays for them. Carry them as overhead and your company ends up paying for the people who run the client's job.
What goes in general conditions?
General conditions are the costs of running a job that don't belong to any one trade. That means things like permitting, dumpsters, temporary toilets, job utilities and small tools, and that's just part of the list. Your superintendent and PM are the biggest general conditions on most jobs.
Price them at this job's actual cost, the same way you price drywall. If the drywall on this job costs twelve grand, you charge twelve grand plus markup.
How do you price the superintendent?
Start with how many weeks the job runs. An eight week job carries eight weeks of superintendent at his weekly cost, whether that's $1,800 or $2,100 or whatever yours is.
That weekly number needs his full labor burden in it. Payroll taxes, unemployment and everything else that rides on top of his wage all belong there.
Save that weekly rate as a saved item in Structur, tied to your general conditions cost code. The next time you add it to an estimate, the description, unit and unit cost come in already filled. Save a finished estimate as a template too, and every new estimate starts with those lines in place.
How do you price the project manager?
Your PM runs several jobs at once, so each job carries only its share of his week. On a given project that might be something like $750 a week.
I always put the superintendent and the PM on two separate lines, and the client could see both. Each estimate line's description shows on the Structur proposal, so the client reads eight weeks of superintendent as its own line.
What happens when the job runs long?
If the schedule goes past the weeks you priced, that's a change order. It carries the superintendent's weekly cost for every extra week.
Put that in your contract, so a client can't tell you that you can't bill him for more super and PM time. Then build the change order in Structur and pull the superintendent line from the job's budget. When the client approves it, the extra weeks show in the budget under approved change orders.
What if you haven't hired a superintendent yet?
Bill the line anyway. Until you hire one, you're the superintendent, so your own weeks on the job go into general conditions.
Even if you're small, start selling jobs that account for a PM and a super.
What stays in overhead?
Your estimator, your office manager and your own salary are overhead. So are the costs of running the office, like internet and your software.
Keep that side to what really belongs there. Overhead and profit can show as their own rows at the bottom of a Structur proposal, where the client sees them. Put too much into overhead and that percentage gets big enough to scare clients away. Moving the super and PM into general conditions keeps that percentage down.
This week, open the bid you're pricing and add two lines under general conditions. One is weeks of superintendent and one is weeks of PM, each at its weekly cost.
More From The Blog
Why Your Team Ignores The SOPs You Wrote
Writing your SOPs is hard. Getting your team to follow them takes a rollout: a walkthrough, a quiz they sign off on and a weekly scorecard.
Read the post 3 min readCost code managementHow To Code A Supplier Statement For Job Costing
Split every supplier statement line by line to the job and the cost code. One materials line can't show you what any part of the job cost.
Read the post 2 min readStandard operating proceduresHow To Run A Construction Knowledge Quiz In An Interview
Run the construction knowledge quiz live, one question at a time, as a conversation. A candidate who hasn't done the work can't keep it going for long.
Read the post 2 min read