Milestone Billing Or Monthly Billing For Contractors?
Bill monthly, on a fixed date, by percentage of completion on a schedule of values, with a deposit up front, change orders every cycle and 5% retainage.
Bill monthly, on a fixed date, by percentage of completion on a schedule of values. Milestone billing creates feast and famine cycles. You wait weeks for a large payment while your costs keep going out every day. Monthly billing gives you a steady rhythm, with money coming in every month.
On a milestone contract, one missing screw can hold up the whole payment. That screw might be 0.0001% of the project, and your cash flow still waits on it.
How does percentage of completion billing work?
Every contract carries one billing date. You might bill every client on the 25th and have them pay by the 10th. Give them a deadline, and if they miss it, they're late.
Each month you bill the percentage complete on each line of the schedule of values. If you're 10% done with the foundation, you bill 10% of that line. AIA contracts already work this way, and it works on residential jobs too.
Structur's pay applications follow that standard construction format. The schedule of values lists every cost code in the approved budget. You set each line as an amount or a percentage. One action can apply the same percentage to every line at once.
What goes on the first invoice?
A deposit, on every project. On residential, 30% is standard, because you're ripping out somebody's kitchen. On private commercial work, ask for 5% to 15%. On franchise or corporate work, call it mobilization or general conditions, which those clients accept more easily.
I did fifty million dollars of commercial projects. I got a deposit on every one, except maybe one or two government jobs. I treat the deposit as billing ahead on the schedule of values, so the job starts out 5% or 10% complete.
Which lines can you bill early?
Some lines can carry more in the first month. General conditions can go out at 20% to 30%, and so can site work. Long lead items like doors, windows, HVAC units and specialty materials can be billed at 40% when they're ordered. That covers the cost of buying them.
If you want to keep it simple, bill 10% across every line. I did that a lot.
Who owns the billing?
The project manager owns it, with the office manager supporting. Before the invoice gets prepared, the superintendent verifies the percent complete, since he's the one on site every day.
Change orders go into every billing cycle. A Structur pay application's schedule of values lists every approved proposal and approved change order. So a signed change order lands on the next pay app.
Attach your lien releases, and follow up within 48 hours of sending the invoice. Most contractors invoice when they remember, miss change orders and skip the follow-up, and that's usually why cash runs short.
How does retainage work?
Retainage of 5% is standard on most commercial contracts. You get paid 95% as you go. You bill the retainage after the punch list is done and the closeout documents are delivered.
You set retainage on each line in Structur, as an amount or a percentage. It's held back on every invoice and reconciled on the final one.
When do you pay your subs?
On the same monthly cycle. Your clients pay you, you pay the subs, and the money moves in one clean loop each month.
Structur lets you switch on lien waivers for each subcontract. A bill against that subcontract waits until the vendor signs the waiver, and then it's open for payment.
How do you make the switch?
Start with the next contract you send. Pick your billing date this week, write it in, and bill that job on the same date every month.
More From The Blog
What Should You Buy Out First On A Job?
Windows, doors, HVAC units, switchgear, steel and engineered lumber get bought out first. Then level the rest against your estimate and sign every sub.
Read the post 3 min readDaily logsHow Many Jobs Can One Superintendent Run?
A superintendent might carry four or five small residential jobs, but on larger, more complex work he really shouldn't run more than two at a time.
Read the post 2 min readStandard operating proceduresHow To Run And Document A Toolbox Talk
A toolbox talk is a short weekly safety meeting on one job-specific topic. How to run one, check if it's required, and keep a signed, dated record.
Read the post 2 min read